BWMS Code type approval tests, System Design Limitations and 24-month self-monitoring records (MEPC.300(72))

Resolution MEPC.300(72) is the Code for approval of ballast water management systems (BWMS), adopted on 2018-04-13. It turned the G8 guidelines into a mandatory code under the Convention. Under operative paragraph 2, the Code takes effect on 2019-10-13, when the associated Convention amendments entered into force.

Code paragraph 1.1 names Administrations and their designated bodies as the primary audience. Manufacturers and shipowners use it for reference. The ship still receives everything the Code produces. The values on the Type Approval Certificate, the records the equipment keeps and the documents held on board all come from here.

This article reads the test conditions, the System Design Limitations (SDL), self-monitoring and the documents on board, in that order. It does not cover port State control results. Those are in the Tokyo MOU report linked below.

Approval does not end the discharge standard, which lasts the life of the ship

Code paragraph 1.5 keeps the role of approval narrow. Approval screens out systems that would fail the regulation D-2 standard. It is not a guarantee that a system works on every ship or in every situation.

a discharge must comply with the D-2 standard throughout the life of the ship

Code paragraph 2.2 restates the regulation D-2 standard below. Both the approval tests and the ship’s discharges are judged against these values.

Target Standard
Viable organisms 50 μm or more in minimum dimension Fewer than 10 per m3
Viable organisms from 10 μm to under 50 μm Fewer than 10 per mL
Toxicogenic Vibrio cholerae (O1, O139) Under 1 cfu per 100 mL, and so on
Escherichia coli Under 250 cfu per 100 mL
Intestinal Enterococci Under 100 cfu per 100 mL

Dates decide how a system approved under older guidelines is treated

The resolution’s operative paragraphs and Code paragraph 1.13 settle how to treat systems approved before the Code.

Date or provision Content
2018-10-28 (operative paragraph 4) Only approvals under the MEPC.174(58) guidelines by this date use the installation clause below
2019-10-13 (operative paragraph 2) The BWMS Code takes effect
2020-10-28 (operative paragraph 4) A system approved by 2018-10-28 may be installed on a ship before this date
Code paragraph 1.13 Systems approved taking into account the MEPC.279(70) guidelines are deemed to meet the Code

Here, installed does not mean the day the work finished. Operative paragraph 5 makes it the contractual date of delivery of the system to the ship. Without such a date, it is the actual delivery date.

Certificate validity and an installed system are looked at separately. The preamble records the practice in MSC.1/Circ.1221. A system manufactured during the certificate’s validity and installed on board need not be replaced when the certificate expires.

Land-based and shipboard tests look at different things

Before testing, the Administration evaluates the manufacturer’s documents (annex Part 1). The test facility must not be owned by or affiliated with the manufacturer or a major component supplier (annex paragraph 2.4). The Administration decides the test sequence (annex paragraph 2.1).

Item Land-based test Shipboard test
Successes At least 5 consecutive per salinity (2.11) 3 consecutive (2.8.8)
Duration Not set At least six months including invalid cycles (2.8.7)
Scale Control and treated tanks of at least 200 m3 each (2.21) Normal ballast volumes, operated at TRC (2.8.4)
Influent standard At least 100,000 organisms/m3 of 50 μm or more (2.33.1) Density over 10 times the D-2.1 maximum (2.8.5)
Who runs it Independent of the manufacturer (2.15) The crew operates and maintains it per the manual (2.7)

TRC is the maximum continuous capacity for which the system is type-approved (Code paragraph 3.17). It is measured at the system inlet, in m3/h. Land-based tests may use a scaled-down model within set limits (annex paragraphs 2.26 and 2.27). If a model has a TRC of 200 m3/h or less, the system cannot be downscaled. A model above 200 m3/h but below 1,000 m3/h allows 1:5, and a model of 1,000 m3/h or more allows 1:100. Either way the test unit cannot go below 200 m3/h.

Test cycles fall into three kinds. A failed cycle ends the whole test (Code paragraph 3.6). An invalid cycle is one where the conditions were not met for reasons outside the system’s control. It does not count, and the test continues (Code paragraph 3.7). If the control water discharge is at or below 10 times the D-2.1 values, the cycle is invalid (annex paragraph 2.45). The test report must include every failed and invalid cycle (annex paragraph 2.59).

The salinity ranges tested decide whether the certificate carries a limit

A certificate with no salinity limit requires testing in all three ranges below (annex paragraph 2.31). Tests in adjacent ranges must be at least 10 PSU apart. Each salinity also has minimum organic and suspended content (annex paragraph 2.29).

Item Marine (28-36 PSU) Brackish (10-20 PSU) Fresh (under 1 PSU)
Dissolved organic carbon Over 1 mg/L Over 5 mg/L Over 5 mg/L
Particulate organic carbon Over 1 mg/L Over 5 mg/L Over 5 mg/L
Total suspended solids Over 1 mg/L Over 50 mg/L Over 50 mg/L

Temperature is assessed across a ballast water range of 0°C to 40°C (2°C to 40°C for fresh water) (annex paragraph 2.46). The assessment may use existing data or models as well as testing (annex paragraph 2.47). That is where it differs from salinity.

Regrowth is evaluated in at least two cycles per salinity (annex paragraph 2.49). The holding time is at least five days (annex paragraph 2.51). At least two cycles per salinity are also run at the manufacturer’s minimum holding time (annex paragraph 2.13). Electrical and electronic sections undergo separate environmental testing (annex Part 3).

SDL does not decide approval and appears on the certificate as an operating range

The ship has two entries to read on the Type Approval Certificate. The names are close, but they come from different places.

Item Limiting Operating Conditions System Design Limitations (SDL)
Basis Code paragraph 6.2 Code paragraphs 3.14 and 6.5, annex Part 6
Meaning Marks that not all Part 2 temperatures and salinities were tested Low and high values for water quality and operating parameters beyond the test items
Effect on approval Approval only with this marking No effect on eligibility (Code 5.5, annex 6.1)
Source of values Refers to the SDL Claimed by the manufacturer, validated under the Administration

SDL makes the manufacturer disclose every parameter the design is sensitive to. The manufacturer claims a low or high value for each, and the Administration evaluates the basis (annex paragraphs 1.14 and 1.15). Validation is independent of the manufacturer. It is not a test to find failure points (annex paragraph 6.2.4). A claim with no low or no high value must be validated too (annex paragraph 6.3).

Annex paragraph 6.4 adds one more reading rule. A manufacturer may include a margin of error in the SDL. So going past an SDL value should not be read as the system immediately being unable to operate. The Administration may take this into account and add restrictions to the certificate. The Code’s examples of such restrictions are UV transmittance, pressure, pressure differentials and Total Residual Oxidants (TRO) (annex paragraph 7.1.7).

Here is a hypothetical case. A ship’s certificate has no salinity limit, and its SDL table has a low UV transmittance value of 60%. Assume this system monitors UV transmittance. If the value falls below the approved range while taking turbid water in a river-mouth port, the system gives an alert and logs it with a time stamp (annex paragraph 5.3.6). The Code does not say what the ship does at that moment. The action has to come from the ballast water management plan and the manufacturer’s manual. What the ship can do before arrival is compare the port’s water with the certificate values.

The equipment keeps the self-monitoring record, not a person

Annex Part 5 sets the minimum items every system records. The Administration may waive items that do not apply and may add items it needs (annex paragraph 5.2).

Group What is recorded Paragraph
General Ship name, IMO number, manufacturer and type, serial number, installation date, TRC, treatment principle 5.3.1
Operation Operating and transition modes including bypass, pump status, outlet flow rate, tank involved 5.3.2
Position, holding Automatic recording recommended, otherwise entered by hand in the ballast water record book 5.3.3
General alerts Shutdown in operation, maintenance required, bypass valve status, mode valve status 5.3.5
Operational alerts A parameter outside its approved range, or a combination outside specifications 5.3.6
SDL parameters Range and alarm values protected by administrator password, with changes and signal loss logged 5.3.8

An operational alert is logged when a combination goes outside specifications even if each single parameter stays within range. Storage has four requirements.

  • The system records proper functioning or failure automatically without user interaction, and time stamps every entry (annex paragraph 5.5).
  • It can produce a summary file for each ballast water operation on demand (annex paragraph 5.5). Formats include text, PDF, Excel and XML (annex paragraph 5.6).
  • It is designed so that stored data cannot be manipulated, and any attempt is recorded. Permanent deletion must not be possible (annex paragraphs 5.7 and 5.8).
  • It stores data for at least 24 months. If the control and monitoring equipment is replaced, earlier data must remain on board for 24 months (Code paragraph 4.20).

The replacement clause has to go into the work plan. If a replacement job has no way to carry the data over, the record breaks. The Code says the means must be provided.

A bypass is recorded in two places, the equipment and the ballast water record book

Emergency bypasses exist to protect the ship and personnel. A bypass must activate an alarm. The event is recorded both by the control and monitoring equipment and in the ballast water record book (Code paragraph 7.2). Internal transfers such as anti-heeling operations are outside this requirement. A system whose internal transfers may affect D-2 compliance, such as circulation or in-tank treatment, must identify those transfers in the record (Code paragraph 7.3).

When the system runs for cleaning, calibration or repair, a visual indication comes on and the equipment records it (Code paragraph 4.9.2). Access beyond routine maintenance requires breaking a seal (Code paragraph 4.9.1). Software changes follow a traceable change procedure (Code paragraph 4.22).

Code paragraph 8.2 and section 4 set the documents on board

Document or record Requirement Paragraph
Copy of the Type Approval Certificate Verified when the International Ballast Water Management Certificate is issued, and the certificate form also says to carry it 8.2.1
Operation, maintenance and safety manual Includes procedures for discharging untreated water on malfunction 8.2.2
Ballast water management plan The procedures for that ship 8.2.3
Installation specifications and drawings Installation drawing, piping and instrumentation diagrams, and so on 8.2.4
Installation commissioning procedures Completion verified before the certificate is issued 8.2.5, 8.3.6
Calibration certificate Certifies the last calibration check, done only by the manufacturer or persons it authorizes 4.10
Maintenance and repair records All maintenance and repairs 4.8

A system that could emit dangerous gases needs redundant gas detection, alarms and an independent shutdown in its space (Code paragraphs 4.5.3 and 4.21). If the system handles dangerous gases, these are items to confirm as well.

Worth confirming

This article read the text as adopted in 2018. It does not cover later amendments to the Code or circulars. It also did not read the regulation D-3 text in MEPC.296(72), which made the Code mandatory.

A footnote to annex paragraph 5.2 says the Organization will develop guidance on the technical template for monitoring parameters and record intervals. The Code gives no record interval figures. The Active Substance approval procedure (G9), sample analysis methods (annex Part 4) and the sampling guidelines (G2) are also not covered by this article. The Code has no pass figures for installation commissioning either. Check actual application against the ship’s certificate and flag State requirements.

You can consult the cited source documents

These links lead to the official publishers of the documents discussed here. Match the edition and provisions cited in the article, and check subsequent amendments and flag-state implementation before applying them.

Bellbook keeps the BWMS calibration certificate and maintenance and repair records ship by ship

Code paragraph 4.8 requires all maintenance and repairs to be recorded, and 4.10 requires a calibration certificate on board. Upload the calibration certificate and the Type Approval Certificate copy to Bellbook's ship document box and add the BWMS as equipment in the PMS, and both records stay with the ship. This does not replace the self-monitoring record inside the equipment.