SIRE 2.0

SIRE 2.0 time limits from inspection request to report publication and the conditions for cancellation and withdrawal

A SIRE 2.0 inspection moves in turn between the vessel operator, the submitting company, the inspector and OCIMF. Each handover has a time limit. Miss some limits and the inspection fails. Some are only recommendations. Some the system moves past on its own. An operator needs to separate these three to decide what to write into its own procedure.

The baseline here is the SIRE 2.0 Conditions of Participation, Policies and Procedures version 1.0 (June 2023). It is supplemented by the Submitting Company process document version 1.0 (March 2023) and the Vessel Operator process document version 1.0 (March 2023). A page number on its own refers to the Conditions of Participation.

Scope: The procedures here are programme rules binding participants in the OCIMF SIRE 2.0 programme. They are not convention or flag-state obligations. The PIQ content and the declaration procedure are covered in a separate article, so this one looks only at the time limits.

Time limits come in three kinds

Stage Number Content Kind Source
Request 30 days A request within 30 days of the last completed inspection needs a legitimate reason Mandatory Page 7
Request 5 companies, 72 hours Up to 5 submitting companies are chosen, and after 72 hours the request moves on System Submitting Company document, page 4
Acceptance 30 days Within 30 days of another booking or completed inspection on the ship, a reason goes to OCIMF Mandatory Page 8
Inspector assignment 48 hours Assignment and reassignment inside 48 hours should not be routine Recommended Pages 8, 10 and 11
Declaration 48 hours, 96 hours PIQ update and declaration at least 48 hours before, ideally 96 hours Recommended Page 7
Physical inspection 8 hours, 10 hours Compiled for 8 hours and never over 10 hours Mandatory Programme Introduction, page 22
CVIQ submission 72 hours Submitted to OCIMF within 72 hours after the physical phase ends Mandatory Page 13
Operator comments 14 days Automatic publication after 14 calendar days from release System Pages 14 and 16

A recommendation is not a light thing. The 48 and 96 hours are recommendations, but a late declaration can lead to cancellation of the booking (pages 7 and 10). Submitting companies are advised to hold an internal policy for cancelling inspections where information arrives late (page 10). No declaration at all is worse. The CVIQ is not generated and cannot reach the inspector’s tablet, and the document calls this a failed inspection (page 10).

A submitting company has four responses (page 8). It accepts and assigns an inspector, accepts only, declines, or does not respond. Declining and not responding both pass the request to the next company. If nobody takes it, the request is cancelled and must be created again (Vessel Operator document, page 9). So a request naming five companies can circulate for 15 days (five times 72 hours) on silence alone. The 15 days is this article’s own calculation.

Where the documents give no number, the company sets one

The first number a reader looks for is how many days before an inspection to make the request. The documents do not give it. Instead page 7 tells the operator to define it in procedure.

  • How long before a planned inspection to make the request
  • How long before to make the declaration for certificates, photographs and PIQ
  • Who may cancel requests and bookings, and in what circumstances

The submitting company defines the same kinds of thing (page 8). These are acceptance criteria, the minimum time for acceptance, the minimum time for assigning an inspector, and exceptions with their approval authority. There is also a recommendation to publish its expectations. So when an operator writes its procedure, it should get the criteria of the submitting companies it works with and set an earlier date.

Inspector assignment has a system check (pages 9 and 10). Red marks conditions under which the inspector should not be assigned, and amber those to avoid. The time-related amber conditions are an inspection of the same ship within the previous 12 months and another inspection within 72 hours. The submitting company can override a rule by selecting a reason (Submitting Company document, page 8).

A repeat inspection has to wait until the previous report is finished

The documents have no separate procedure called re-inspection. Inspecting the same ship again is a new request. Page 7 sets two conditions.

  1. The report of the previous inspection must have been published or withdrawn.
  2. A request within 30 days of the previous inspection’s completion needs a legitimate reason at the time of request.

Note that the two conditions run on different clocks. Count the dates on a hypothetical product tanker.

Hypothetical date Event
2 March The physical inspection ends
5 March The CVIQ submission limit (72 hours)
12 March Assume the submitting company finishes review and releases the draft to the operator
26 March Automatic publication unless the operator publishes earlier (14 days)
1 April Day 30 from 2 March

This ship is held by the first condition before 26 March. After that, the second condition remains until 1 April. If the submitting company opens a resubmission on 25 March and releases the draft again on 30 March, automatic publication moves to 13 April. Then even after the 30 days the first condition blocks a request. These dates are hypothetical. The documents do not say how the first day of the 30 is counted.

The 30-day rule comes with an exception and a follow-on risk. The recommendation on page 8 is to avoid an inspection within 30 days unless the draft or published report was withdrawn. A repeat inspection at a short interval can also come back as a withdrawal. Covering inspection on page 15 includes the case where OCIMF’s inquiry finds too little time passed after the previous inspection to resolve its observations.

Cancellation closes the moment the physical inspection starts

Timing Who Conditions and result
Request not yet accepted Operator The request can be removed (page 8; Vessel Operator document, page 23)
After booking, before physical phase Operator or submitting company A legitimate reason is given. Parties are emailed and the CVIQ and data are removed from the tablet (page 9)
After the physical phase starts Nobody can cancel If the master or operator demands a stop, the CVIQ up to that point is submitted (page 9)

The last row matters. Breaking off an inspection does not erase the record. Unfinished questions are filled with Not Answerable and the report name takes (I) (Submitting Company document, pages 15 to 17). Nor can the report be withdrawn for this reason (pages 15 and 16).

Changing the inspector closes at the same line. If the assigned inspector cannot attend, the submitting company assigns another or cancels the booking (page 11). The change is possible until the physical phase starts (Submitting Company document, page 10).

If an error in operator data is found after the declaration, cancellation can be the tool. Page 5 of Draft Inspection Report Validation version 1.0 says operator data cannot be corrected after the declaration without cancelling the inspection and booking a new one.

Discussion outside the system does not stop the draft’s 14 days

Once the CVIQ reaches OCIMF it is merged with operator content and becomes the draft report (page 13). From then on the only way to change an answer is resubmission. Untagged inspector photographs can no longer be added. The submitting company checks quality and then releases the draft to the operator. Release is the submitting company’s warranty that the draft is free of inspector errors (page 13).

The operator’s 14 days start at this release (page 14). In status terms, that is when the report becomes Submitter Validated (Submitting Company document, page 32). The operator appends initial comments in this period. It may also publish earlier (page 16).

If the operator suspects an inspector error, it tells the submitting company. There is no channel for this in the system, so it happens outside (page 15). That is where the trap sits. The sentence is on page 32 of the Submitting Company document.

this will not affect the 14 days timing

If the submitting company agrees, it recalls the draft and opens a resubmission. If it rejects the point, the report publishes on day 14 (page 14). When a resubmission releases the draft again, the 14 days start anew (page 32). A resubmission can change only the questions the submitting company selects, and the original inspector makes the change. If that inspector is no longer active it goes to OCIMF QA (Submitting Company document, pages 22 and 24). Operator comments already entered are saved, but access is removed until the draft is released again (page 28).

So once an error is found, count the dates first and do not wait for the discussion to end. Enter comments within the limit. After publication neither the report nor the comments can be corrected (page 16). Later comments can be added, but they accumulate and cannot be edited or deleted.

Withdrawal is not a remedy for dissatisfaction

If a published report has significant errors that make it unreliable or misleading, withdrawal is the only option (page 15). The submitting company withdraws it, or OCIMF does with notice to the submitting company. The submitting company can also withdraw at the draft stage (Submitting Company document, page 29).

Grounds for withdrawal (page 15) Not grounds for withdrawal (pages 15 and 16)
Significant errors that make the report unreliable The master or operator ordered the inspection stopped
An inspection in circumstances that could be seen as a conflict of interest The master or operator asked for withdrawal
A report at odds with facts verified after publication (Conflicted report) Dissatisfaction with the results
A Covering inspection after an OCIMF inquiry
A participant becoming subject to sanctions

On withdrawal, emails go to recipients who downloaded the report, the submitting company, the operator and the inspector. OCIMF refunds the cost of buying a withdrawn report (page 15). Withdrawal also opens the door to the next inspection. It satisfies the first condition above and falls within the exception to the 30-day recommendation.

Worth confirming

The wording differs on when the 14 days restart after a resubmission. Page 28 of the Submitting Company document and page 33 of the Vessel Operator document put it at the status becoming Resubmission, and page 32 of the Submitting Company document puts it at the release. The calculation above follows page 32. Where a few days matter, confirm with the submitting company.

The documents do not say whether a cancelled booking counts as another booking under the 30-day rule on page 8. If you cancel and rebook, ask the submitting company whether a reason is needed.

Some things are not covered by this article. We searched the OCIMF documents in the corpus and found no numeric limit for the submitting company to review and release a draft. For inspector resubmissions they only say to act promptly (page 5). So 12 March in the example is an assumption. We also found no validity period for a published report. The criteria by which report recipients ask for a repeat inspection are not in these documents either. All documents used here are version 1.0, so check later editions with OCIMF.

You can consult the cited source documents

These links lead to the official publishers of the documents discussed here. Match the edition and provisions cited in the article, and check subsequent amendments and flag-state implementation before applying them.

Bellbook fills in a 14-day comment deadline on each VETTING finding

Discussion outside the system does not stop the 14 days. Bellbook records SIRE 2.0 findings by chapter, question number and NOC. Enter the draft release date and the open findings move to 14 days after it. Before release, 14 days after the inspection date stands in as a provisional deadline. It also helps with draft operator comments and English translation. Entry and publication happen in the OCIMF system.